PROJECT OVERVIEW

Harper’s first project in Georgia, the upgrades to the Hartwell WTP involved work in the filters and administration building. The Harper team worked closely with the plant operators to ensure work did not interrupt operations at the active plant, while installing yard pipe, new filters, and building a new clearwell. Due to the age of the plant, the project involved extensice concrete repairs in the existing clearwell under the administration building and work in confined spaces. The result of the project was additional capacity for the plant, allowing continued growth in the service area.

Owner

  • City of Hartwell