GHS MD 360 Simpsonville

PROJECT OVERVIEW

MD 360 in Simpsonville was the first building to be constructed for the GHS MD360 Convenient Care Facilities. GHS possessed a strong desire to open the 13,000 SF facility in October of 2009. The accelerated schedule required working 6 days/week, 10 hours/day. The project team overcame unforeseen site conditions resulting from unsuitable soils. Harper provided systems and materials cost/constructability analysis even as the Civil Work commenced. A Civil Package and Structural Package was utilized for pricing and construction as the Owner and Designer finalized building design and finish selections. ProAxis Therapy occupied approximately 5,000 SF of the building simultaneously with the Convenient Care operation.

Owner

  • Greenville Health System